Special meetings of the Southwestern Community College board of trustees were held on November 26, 2013, and December 3, 2013, to discuss and approve plans related to the construction of a new residence hall on campus. Due to time constraints of board members, the meetings were held electronically.

The first item on the agenda at the November 26 meeting was consideration of earthwork and major utilities for the residence hall construction project. Two bids were received. Following discussion, the board approved the lowest bid of $721,680 from Seamus Excavating.

Next on the agenda was consideration of footings and foundations for the residence hall project. The board approved the lowest bid of $143,400 from Jensen Builders.

At the December 3 board meeting, the board held public hearings for topping slabs, precast hollow core plank, masonry, miscellaneous metals, wood framing, joists, trusses, sheathing, building wrap, and windows, as well as for the elevator project, for the new residence hall construction project. No oral or written objections were heard or submitted for either project.

Following the public hearings, the board approved the lowest bid of $587,000, from Lansink Construction, for the construction for topping slabs, precast hollow core plank, masonry, miscellaneous metals, wood framing, joists, trusses, sheathing, building wrap, and windows.

O’Keefe Elevator was approved for the elevator project. O’Keefe had the lowest bid, at $69,500, of two submitted bids.